RAIL TRANSPORT

Rail Systems

Solutions for stations, signalling, communications and on-board auxiliary power, assessed together with environmental conditions, maintenance access and operational continuity.

Request a quote →
Rail Systems critical-power infrastructure

OPERATING REQUIREMENTS

Design starts with the consequences of an outage.

The appropriate architecture is defined by critical functions, load behaviour, maintenance paths and site conditions, as well as equipment ratings.

Power-continuity requirements

  • Uninterrupted supply for signalling and communications
  • Remote alarm and status monitoring at distributed sites
  • System construction suited to vibration, temperature and limited maintenance access
  • Controlled power continuity for station and trackside equipment

Critical loads

  • Signalling and point control
  • Communications and passenger information
  • Station control and security systems
  • On-board or stationary auxiliary DC/AC loads

PROPOSED ARCHITECTURE

A traceable chain from source to critical load.

  1. Grid or traction auxiliary supply
  2. UPS/rectifier and battery
  3. Critical AC/DC distribution
  4. Local monitoring
  5. Signalling and communications

This diagram shows a typical solution approach. Final topology is established using the load list, single-failure criteria, operating philosophy and approved project data.

ENGINEERING DECISIONS

Redundancy, protection and monitoring are assessed together.

Redundancy strategy

  • Centralised or distributed redundant supply points
  • Load transfer and bypass planning during maintenance
  • A/B supply options for critical communications

Protection strategy

  • Voltage-drop and protection coordination based on cable distances
  • DC pole and short-circuit protection
  • Enclosures, terminals and mechanical protection suited to site conditions

Control and monitoring

  • Remote station alarm summaries
  • Battery voltage, temperature and supply condition
  • Dry-contact or communications interfaces to central monitoring

PROJECT INPUTS

What information is required for correct selection?

Share the information available at the initial quotation stage. Outstanding technical data can be clarified during the site survey and engineering review.

  • Track, station and equipment layout
  • AC/DC load list for each supply point
  • Autonomy and supply-restoration scenarios
  • Cable distances, environment and vibration conditions
  • Central monitoring requirements and alarm matrix

EKA DELIVERY SCOPE

Defined responsibilities from calculation to commissioning.

  • Capacity calculations for each supply point
  • UPS/rectifier, battery and panel integration
  • Enclosures, racks and connection accessories
  • Site labelling and maintenance documentation

FAT — factory acceptance testing

  • Load and alarm scenarios
  • Battery charging and bypass functions
  • Mechanical and connection checks
  • Remote-monitoring signal simulation

SAT and commissioning

  • Site cable and earthing checks
  • Voltage-drop and load measurements
  • End-to-end central-monitoring tests
  • Commissioning and maintenance-team training

Discuss your facility’s requirements.

Share the critical-load list, autonomy target and existing power architecture with our engineering team.

Request a quote →All sector solutions →